Wednesday, January 29, 2020

Control cycles-a general model Essay Example for Free

Control cycles-a general model Essay A general model of organizational control includes four components that can operate in a continuous cycle and can be represented as a wheel. These elements are: 1. Setting a goal. Project goal setting goes beyond overall scope development to include setting the project baseline plan. The project baseline is predicated on an accurate. Work Breakdown Structure (WBS) process. Remember that WBS establishes all the deliverables and work packages associated with the project, assigns the personnel responsible for them, and creates a visual chart of the project from highest level down through the basic task and subtask levels. The project baseline is created as each task is laid out on a network diagram and resources and time durations are assigned to it. 2. Measuring progress. Effective control systems require accurate project measurement mechanisms. Project managers must have a system in place that will allow them to measure the ongoing status of various project activities in real time. We need a measurement system that can provide information as quickly as possible. What to measure also needs to be clearly defined. Any number of devices allow us to measure one aspect of the project or another; however, the larger question is whether or not we are getting the type of information we can really use. 3. Comparing actual with planned performance. When we have some sense of the original baseline (plan) and a method for accurately measuring progress, the next step is to compare the two pieces of information. A gap analysis can be used as a basis for testing the project’s status. Gap analysis refers to any measurement process that first determines the goals and then the degree to which the actual performance lives up to those goals. The smaller the gaps between planned and actual performance, the better the outcome. In cases whe re we see obvious differences between what was planned an what was realized, we have a clear-cut warning signal. 4. Taking action. Once we detect significant deviations from the project plan, it becomes necessary to engage in some form of corrective action to minimize or remove the deviation. The process of taking corrective action is generally straightforward. Corrective action can either be relatively minor or may involve significant remedial steps. At its most extreme, corrective action may even involve scuttling a nonperforming project. After corrective action, the monitoring and control cycle begins again. The control cycle is continuous. As we create a plan, we begin measurement efforts to chart progress and compare stages against the baseline plan. Any indications of significant deviations from the plan should immediately trigger an appropriate response, leading to a reconfiguration of the plan, reassessment of progress, and so on. Project monitoring is continuous, full-time cycle of target setting, measuring, correcting, improving, and remeasuring. MONITORING PROJECT PERFORMANCE As we discovered in the chapters on project budgeting and resource management, once we have established a project baseline budget, one of the most important methods for indicating the ongoing status of the project is to evaluate it against the original budget projections. For project monitoring and control, both individual task budgets and the cumulative project budget are relevant. The cumulative budget can be broken down by time over the project’s projected duration. The Project S-Curve: A Basic Tool As a basis for evaluating project control techniques, let us consider a simple example. Assume a project (Project Sierra) with four work packages (Design, Engineering, Installation, and Testing), a budget to complete of $80,000, and an anticipated duration of 45 weeks. To determine project performance and status, a straightforward time/cost analysis is often our first choice. Here the project’s status is evaluated as a function of the accumulated costs and labor hours or quantities plotted against time for both budgeted and actual amounts. We can see that time (shown on the x, or horizontal, axis) is compared with money expended (shown on the y, or vertical, axis). The classic project S-curve represents the typical form of such a relationship. Budget expenditures are initially low and ramp up rapidly during the major project execution stage, before starting to level off again as the project gets nearer to its completion. Cumulative budget projections for Project Sierra have been plotted against the project’s schedule. The S-curve figure represents the project budget baseline against which budget expenditures are evaluated. Monitoring the status of a project using S-curves becomes a simple tracking problem. At the conclusion of each given time period (week, month, or quarter), we simply total the cumulative project budget expenditures to date and compare them with the anticipated spending patterns. Any significant deviations between actual and planned budget spent reveal a potential problem area. Simplicity is the key benefit of S-curve analysis. Because the projected project baseline is established in advance, the only additional data shown are the actual project budget expenditures. The S-curve also provides real-time tracking information in that budget expenditures can be constantly updated and the new values plotted on the graph. Project information can be visualized immediately and updated continuously, so S-curves offer an easy-to-read evaluation of the project’s status in a timely manner. (The information is not necessarily easily interpreted, however, as we shall see later.) Our Project Sierra example can also be used to illustrate how S-curve analysis is employed. Suppose that by week 21 in the project, the original budget projected expenditures of $50,000. However, our actual project expenditures totaled only $40,000. In effect, there is a $10,000 budget shortfall, or negative variance between the cumulative budgeted cost of the project and its cumulative actual cost. In the table it shows the track of budgeted expenditures with actual project costs, including identifying the negative variance shown at week 21. In this illustration, we see the value of S-curve analysis as a good visual method for linking project costs (both budgeted and actual) over the project’s schedule. S-CURVE DRAWBACKS When project teams consider using S-curves, they need to take the curve’s significant drawbacks into consideration as well as their strengths. S-curves can identify positive and negative variance (budget expenditures above or below projections), but they do not allow us to make reasonable interpretations as to the cause of variance. Consider the S-curve shown. The actual budget expenditures have been plotted to suggest that the project team has not spent the total planned budget money to date (there is negative   variance). However, the question is how to interpret this finding. The link between accumulated project costs and time is not always easily resolved. Is the project team behind schedule (given that they have not spent sufficient budget to date) or might there be alternative reasons for the negative variance? Assume that your organization tracks project costs employing an S-curve approach and uses that information to assess the status of an ongoing project. Also assume that the project is to be completed in 12 months and has a budget of $150,000. At the six-month checkup, you discover that the project S-curve shows significant shortfall; you have spent far less on the project to date than was originally budgeted. Is this good or bad news? On the surface, we might suppose that this is a sign of poor performance; we are lagging far behind in bringing the project along and the smaller the amount we have spent to date is evidence that our project is behind schedule. On the other hand, there are any number of reasons why this circumstance actually might be positive. For example, suppose that in running the project, you found a cost-effective method for doing some component of the work or came across a new technology that significantly cut down on expenses. In that case, the time/cost metric may not only be misused, but might lead to dramatically inaccurate conclusions. Likewise, positive variance is not always a sign of project progress. In fact, a team may have a serious problem with overexpenditures that could be interpreted as strong progress on the project when in reality it signals nothing more than their inefficient use of project capital resources. The bottom line is this: Simply evaluating a project’s status according to its performance on time versus budget expenditures may easily lead us into making inaccurate assumptions about project performance. Milestone Analysis Another method for monitoring project progress is milestone analysis. A milestone is an event or stage of the project that represents a significant accomplishment on the road to the project’s completion. Completion of a deliverable (a combination of multiple project tasks), an important activity on the project’s critical path, or even a calendar date can all be milestones. In effect, milestones are road markers that we observe on our travels along the project’s life cycle. There are several benefits to using milestones as a form of project control. 1. Milestones signal the completion of important project steps. A project’s milestones are an important indicator of the current status of the project under development. They give the project team a common language to use in discussing the ongoing status of the project. 2. Milestones can motivate the project team. In large projects lasting several years, motivation can flag as team members begin to have difficul ty seeing how the project is proceeding overall, what their specific contribution has been and continues to be, and how much longer the project is likely to take. Focusing attention on milestones helps team members become more aware of the project’s successes as well as its status, and they can begin to develop greater task identity regarding their work on the project. 3. Milestones offer points at which to reevaluate client needs and any potential change requests. A common problem with many types of projects is the nature of repetitive and constant change requests from clients. Using project review milestones as formal â€Å"stop points,† both the project team and the clients are clear on when they will take midcourse reviews of the project and how change requests will be handled. When clients are aware of these formal project review points, they are better able to present reasonable and well-considered feedback (and specification change requests) to the team. 4. Milestones help coordinate schedules with vendors and suppliers. Creating delivery dates that do not delay project activities is a common challenge in scheduling delivery of key project components. From a resource perspective, the project team needs to receive supplies before they are needed but not so far in advance that space limitations, holding and inventory costs, and in some cases spoilage are problems. Hence, to balance delays of late shipments against the costs associated with holding early deliveries, a well-considered system of milestones creates a scheduling and coordinating mechanism that identifies the key dates when supplies will be needed. 5. Milestones identify key project review gates. For many complex projects, a series of midterm project reviews are mandatory. For example, many proj ects that are developed for the U.S. government require periodic evaluation as a precondition to the project firm receiving some percentage of the contract award. Milestones allow for appropriate points for these review. Sometimes the logic behind when to hold such reviews is based on nothing more than the passage of time (â€Å"It is time for July 1 review†). For other projects, the review gates are determined based on completion of a series of key project steps (such as the evaluation of software results from the beta sites). 6. Milestones signal other team members when their participation is expected to begin. Many times projects require contributions from personnel who are not part of the project team. For example, a quality assurance individual may be needed to conduct systems tests or quality inspection and evaluations of work done to date. The quality supervisor needs to know when to assign a person to our project, or we may find when we reach that milestone that no on e’s available to help us. Because the QA person is not part of the project team, we need to coordinate his or her involvement in order to minimize disruption to the project schedule. 7. Milestones can delineate the various deliverables developed in the work breakdown structure and therefore enable the project team to develop a better overall view of the project. You then are able to refocus efforts and function-specific resources toward the deliverables that show signs of trouble, rather than simply allocating resources in a general manner. For example, indications that the initial project software programming milestone has been missed allows the project manager to specifically request additional programmers downstream, in order to make up time later in the project’s development. Problems with Milestones Milestones, in one form or another, are probably the simplest and most widely used of all project control devices. Their benefits lie in their clarity; it is usually easy for all project team members to relate to the idea of milestones as a project performance metric. The problem with them is that they are a reactive control system. You must first engage in project activities and then evaluate them relative to your goal. If you significantly underperform your work to that point, you are faced with having to correct what has already transpired. Imagine, for example, that a project team misses a milestone by a large margin. Not having received any progress reports up until the point that the bad news becomes public, the project manager is probably not in a position to craft an immediate remedy for the shortfall. Now, the problems compound. Due to delays in receiving the bad news, remedial steps are themselves delayed, pushing the project farther behind. EARNED VALUE MANAGEMENT An increasingly popular method used in project monitoring and control consists of a mechanism that has become known as Earned Value Management (EVM). The origins of EVM date to the late 1960s when U.S. government contracting agencies began to question the ability of contractors to accurately track their costs across the like of various projects. As a result, after 1967, the Department of Defense imposed 35 Cost/Schedule Control Systems Criteria that suggested, in effect, that any future projects procured by the U.S. government in which the risk of cost growth was to be retained by the government must satisfy these 35 criteria. In the more than 30 years since its origin, EVM has been practiced in multiple settings, by agencies from governments as diverse as Australia, Canada, and Sweden, as well as a host of project-based firms in numerous industries. Unlike previous project tracking approaches, EVM recognize that it is necessary to jointly consider the impact of time, cost, and project performance on any analysis of current project status. Put another way: Any monitoring system that only compares actual against budgeted cost numbers ignores the fact that the client is spending that money to accomplish something-create a project. Therefore, EVM reintroduces and stresses the importance of analyzing the time element in project status updates. Time is important because it becomes the basis for determining how much work should be accomplished at certain milestone points. EVM also allows the project team to make future projections of project status based on its current state. At any point in the project’s development we are able to calculate both schedule and budget efficiency factors (the efficiency with which budget is being used relative to the value that is being created) and use those values to make future projections about the estimated cost and schedule to project completion. We can illustrate the advance in the project control process that Earned Value represents by comparing it to the other project tracking mechanisms. If we consider the key metrics of project performance as those success criteria discussed in Chapter 1 (scheduling, budget, and performance), most project evaluation approaches tend to isolate some subset of the overall success measure. For example, project S-curve analysis directly links budget expenditures with the project schedule. Again, the obvious disadvantage to this approach is that it ignores the project performance linkage. Project control charts such as tracking Gantt charts link project performance with schedule but may give budget expenditures short shrift. The essence of a tracking approach to project status us to emphasize project performance over time. While the argument could be made that budget is implicitly assumed to be spent in some preconceived fashion, this metric does not directly apply a link between the use of time and performance factors with project cost. Earned value, on the other hand, directly links all three primary project success metrics (cost, schedule, and performance). This methodology is extremely valuable because it allows for regular updating of a time-phased budget to determine schedule and cost variances, as identified by the regular measurement of project performance. Terminology for Earned Value Following are some key concepts that allow us to calculate Earned Value and use its figures to make future project performance projections. PVPlanned value. A cost estimate of the budgeted resources scheduled across the project’s life cycle (cumulative baseline). EVEarned value. This is the real budgeted cost, or â€Å"value,† of the work that has actually been performed to date. ACActual cost of work performed. The cumulative total costs incurred in accomplishing the various project work packages. SPISchedule Performance Index. The earned value to date divided by the planned value of work scheduled to be performed (EV/PV). This value allows us to calculate the projected schedule of the project to completion. CPICost Performance Index. The earned value divided by the actual, cumulative cost of the work performed to date (EV/AC). This value allows us to calculate the projected budget to completion. BACBudgeted cost at completion. This represents the total budget for a project. Creating Project Baselines The first step in developing an accurate control process is to create the project baselines against which progress can be measured. Baseline information is critical regardless of the control process we employ, but baselines are elemental when performing EVM. The first piece of information necessary for performing earned value is the planned value; that is, the project baseline. The PV should comprise all relevant project costs, the most important of which are personnel costs, equipment and materials, and project overhead, sometimes referred to as level of effort. Overhead costs (level of effort) can include a variety of fixed costs that must be included in the project budget, including administrative or technical support, computer work, and other staff expertise use (such as legal advice or marketing). The actual steps in establishing the project baseline are fairly straightforward and require two pieces of data: the Work Breakdown Structure and a time-phased project budget. 1. The W ork Breakdown Structure identified the individual work packages and tasks necessary to accomplish the project. As such, the WBS allowed us to first identify the individual tasks that would need to be performed. It also gave us some understanding of the hierarchy of tasks needed to set up work packages and identify personnel needs (human resources) in order to match the task requirements to the correct individuals capable of performing them. 2. The time-phased budget takes the WBS one step further: It allows us to identify the correct sequencing of tasks, but more importantly, it enables the project team to determine the points in the project when budget money is likely to be spent in pursuit of those tasks. Say, for example, that our project team determines that one project activity, Data Entry, will require a budget of $20,000 to be completed, and further, that the task is estimated to require 2 months to completion, with the majority of the work being done in the first month. A ti me-phased budget for this activity might resemble the following: Activity| Jan| Feb| †¦| Dec| Total| Data Entry| $14,000| $6,000| | -0-| $20,000| Once we have collected the WBS and applied a time-phased budget breakdown, we can create the project baseline. The result is an important component of earned value because it represents the standard against which we are going to compare all project performance, cost, and schedule data as we attempt to assess the viability of an ongoing project. This baseline, then, represents our best understanding of how the project should progress. How the project is actually doing, however, is, of course, another matter. Why Use Earned Value? Assume that it is now week 30 of the project and we are attempting to assess the project’s status. Also assume that there is no difference between the projected project costs and actual expenditures; that is, the project budget is being spent within the correct time frame. However, upon examination, suppose we were to discover that Installation was only half-completed and Project Testing had not yet begun. This example illustrates both a problem with S-curve analysis and the strength of EVM. Project status assessment is only relevant when some measure of performance is considered in addition to budget and elapsed schedule. Consider the revised data for Project Sierra. Note that as of week 30, work packages related to Design and Engineering have been totally completed, whereas the Installation is only 50% done, and Testing has not yet begun. These percentage values are given based on the project team or key individual’s assessment of the current status of work package completion. The question now is: What is the earned value of the project work done to date? As of week 30, what is the status of this project in terms of budget, schedule, and performance? Calculating the earned value for these work packages is a relatively straightforward process. We can modify the previous table to focus exclusively on the relevant information for determining earned value. The planned budget for each work package is multiplied by the percentage completed in order to determine the earned value to date for the work packages, as well as for the overall project. In this case, the earned value at the 30-week point is $51,000. We can compare the planned budget against the actual earned value using the original project budget baseline. This process allows us to assess a more realistic determination of the status of the project when the earned value is plotted against the budget baseline. Compare this figure with the alternative method, in which negative variance is calculated, with no supporting explanation as to the cause or any indication about whether this figure is meaningful or not. Recall that by the end of week 30, our original budget projections suggested that $68,000 should have been spent. Instead, we are projecting a shortfall of $17,000. In other words, we are not only showing a negative variance in terms of money spent on the project, but also in terms of value created (performance) of the project to date. Unlike the standard S-curve evaluation, EVM variance is meaningful because it is based not simply on budget spent, but value earned. A negative variance of $10,000 in budget expenditures may or may not signal cause for concern; however, a $17,000 shortfall in value earned on the project to date represents a variance of serious consequences. Steps in Earned Value Management There are five steps in Earned Value Management (EVM): 1. Clearly define each activity or task that will be performed on the project, including its resource needs as well as a detailed budget.As we demonstrated earlier, the Work Breakdown Structure allows project teams to identify all necessary project tasks. It further allows for each task to be assigned its own project resources, including equipment and materials costs, as well as personnel assignments. Finally, coupled with the task breakdown and resource assignments, it is possible to create the budget figure or cost estimate for each project task. 2. Create the activity and resource usage schedules. These will identify the proportion of the total budget allocated to each task across a project calendar. Determine how much of an activity’s budget is to be spent each month (or other appropriate time period) across the project’s projected development cycle. Coupled with the development of a project budget should be its direct linkage to the project schedule. The determination of how much budget money is to be allocated to project tasks is important. Equally important is the understanding of when the resources are to be employed across the project’s development cycle. 3. Develop a â€Å"time-phased† budget that shows expenditures across the projects life.The total (cumulative) amount of the budget becomes the project baseline and is referred to as the planned value (PV). In real terms, PV just means that we can identify the cumulative budget expenditures planned at any stage in the project’s life. The PV, as a cumulative value, is derived from addin g the planned budget expenditures for each preceding time period. 4. Total the actual costs of doing each task to arrive at the actual cost of work performed (AC).We can also compute the budgeted values for the tasks on which work is being performed. This is referred to as the earned value (EV) and is the origin of the term for this control process. 5. Calculate both a project’s budget variance and schedule variance while it is still in process.Once we have collected the three key pieces of data (PV, EV, and AC), it is possible to make these calculations. The schedule variance is calculated by the simple equation: SV = EV – PV, or the difference between the earned value to date minus the planned value of the work scheduled to be performed to date. The budget, or cost, variance is calculated as: CV = EV – AC, or the earned value minus the actual cost of work performed. USING EARNED VALUE TO MANAGE A PORTFOLIO OF PROJECTS Earned Value Management can work at the portfolio level as well as with individual projects. The process simply involves the aggregation of all earned value measures across the firm’s entire project portfolio in order to give an indication as to the efficiency with which a company is managing its projects. Other useful information contained in the Portfolio Earned Value Management table includes the total positive variances for both budget and schedule, as well as determination of the relative schedule and cost variances as a percentage of the total project portfolio. The use of Earned Value Management for portfolio tracking and control offers top management an excellent window into the firm’s ability to efficiently run projects, allows for comparisons across all projects currently in development, and isolates both the positive and negative variances as they occur. All of this is useful information for top-level management of multiple projects.

Tuesday, January 21, 2020

Revelation Essay -- essays research papers

The creation of the earth and all that is within the earth is mysterious yet miraculous at the same time. Although there are probably hundreds of different accounts, they all seem to be different while almost identical in text. I will be comparing and contrasting between account one and account two in the book of Genesis. In the beginning, according to Genesis in the bible.   Ã‚  Ã‚  Ã‚  Ã‚  In the two creation accounts God is portrayed in two different ways. In the first account God is portrayed as an ultimate or Supreme Being that creates the world by fiat, which are divine spoken words. An example of this is found in Genesis 1:3, which says; â€Å"Then God said, â€Å"let there be light†; and there was light.† This is the fiat command that creates light in the first account of creation and demonstrates the supreme power of God. In the second Genesis account God is portrayed as a much more mortal being, a concept called anthropomorphism. In Genesis 2:7 God creates man, but it wasn’t done through fiat. It says, â€Å"Lord God formed man from the dust of the ground, and breathed into his nostrils the breath of life; and the man became a living being.† This account of God creating man is much different from the first account because God is physlically- taking part in creating man instead of using powers by way of fiat. Another instance that portrays God as more humanlike is found in Genesis 2:8 where it says God â€Å"planted† the garden in Eden. The use of the word â€Å"plan...

Monday, January 13, 2020

Literature in the Dark Ages: the Apocrypha

Professor Rodgers Humanities I November 5, 2010 Literature in the Dark Ages: The Apocrypha The Dark ages is referred to as such for many reasons there was plague and sickness that hit humanity during this time and people lived in fear to name a few. But one main reason is the fact that not much information exists about this period in history. Nearly all the ancient critical texts were lost during the Middle Ages. Emperor Flavius Juvianus ordered the burning of Antioch Library.Tons of books were burnt. Pagan temples and libraries were looted or burnt down (1). During the Dark Ages the literature by clergy was produced and preserved more than any other literature. The church was considered the authority on intellect at the time so it was there works that were reproduced in the greatest volume. Clergy therefore dominated literature during this time period. It was in the Dark Ages that there were records of as many as 200 epistles and accounts of the life of Jesus Christ that were said t o have been written.Only 27 were preserved. Of the 193 that were discarded Claytor 2 some people considered them to be fiction pieces of literature, some esteemed them as true and to some they were thought to be fraudulent. The writings that were believed to have been oppressed by Christians during the Dark ages are esteemed by some as lost spiritual teachings. In fact some of these teachings were discovered in 1945 and they expounded on the teachings that are recorded in the bible.They speak of a secret gospel of Mark, secret teachings of John, an account of the Gospels written by Thomas, the Apocalypse of Paul, as well as spiritual insight written by a woman which is called Pistils Sophia. These teachings are by a group called Gnostics. Gnostics were Christians whose belief system was based more upon knowledge than faith. Their name is derived the word Gnosis which is spiritual insight. They heavily embraced the hidden writings.It is likely that due to their Criticisms and differe nces with the Roman Orthodox church that members of the Gnostic sect were burned at the stake and many of their writings destroyed by the Church. Before the discovery of Gnostic writings, our only knowledge of additional accounts of the life and death of Jesus Christ came from a letter written by Church Father Clement of Alexandria (150 AD – 211 AD). In the letter Father Alexandria quotes this secret gospel and refers to it as â€Å"a more spiritual gospel for the use of those who were being perfected.    He said, â€Å"It Claytor 3 even yet is most carefully guarded [by the church at Alexandria], being read only to those who are being initiated into the great mysteries. (2). It is important to note that while Father Alexandria was a proponent of Gnosis, which was a knowledge or insight into the infinite, he rejected the concept as defined by the Gnostic sect. The oppressed writings were considered by some scholars as According to the Early Christian Church the additional writings of the life of Jesus were considered useful but were omitted from records because they weren’t considered to be divinely inspired.The gospels were separated into two categories. They are considered either canonical or non-canonical. The canonical writings are those that were included in the gospels in the bible. The non-canonical were called were considered apocryphal. The word Apocrypha literally means hidden writings. While the different branches of the early church disagreed about which writings were canonical and which were apocryphal they all subscribed to the belief that some writings were divinely inspired by God and others were not. Within the apocryphal writings are accounts of the infancy of Jesus in which they account the childhood of Jesus.There are those that give different perspectives of the passions and the Gospel of Thomas records many sayings of Jesus that are Claytor 4 not included in the bible. The early Christian church deemed many of these writ ings useful but do not believe all were divinely inspired. There are those who believe the lost writings are fraudulent or fiction works. Some of them that subscribe to this belief have concluded that, whether canonical or apocryphal, none of the accounts of the lives of Jesus are true.They believe that by omitting 173 of 200 accounts of the life of Jesus the church proves that it used the writings they selected to merely maintain their power and control. Edward Gibbon, a historian whose work has been heavily criticized by the Christian church, wrote â€Å"The origin of these fraudulent documents was none other than the church. Gibbon tells us: â€Å"Orthodox theologians were tempted, by the assurance of impunity, to compose fictions, which must be stigmatized with the epithets of fraud and forgery. They ascribed their own polemical works to the most venerable names of Christian antiquity. Others who challenge the validity of these writings are Christians who believe some accounts to be true but not others. J. G. Davis, A Christian teacher of Theology, wrote in his book The Early Christian Church â€Å"(they are merely) another genre of literature, devised for reading by the faithful during their leisure time, and corresponding in some ways to the novels of a later era. † Claytor 5 The oppressed ancient writings of Christianity are very controversial.There are little to no facts about the writings that are not debated, disagreed upon or refuted in some way. What is clear is that there are some writings about the life of Jesus that are either currently in existence or evidently existed at some time in history, although the number of apocryphal writings is uncertain. It is also certain that these writings give an account of the same occurrences as those considered canonical by the early Christian church. They are closely related writings that are recorded in the bible and considered by Christians as the true accounts of the life of Jesus.Claytor 6 Cited Workshttp://reluctant-messenger. com/Lost-Doctrines-Christianity003. htm  Ã‚  The Early Christian Church, p. 83 (1965). History of Christianity, p. 598http://www. gnosis. org/library/strom2. htm

Sunday, January 5, 2020

The Devil in Joyce Carol Oates Where Are You Going,...

The Devil in Joyce Carol Oates Where Are You Going, Where Have You Been? Her name is Connie, and she is not unlike many girls of the time she lives in. She is vain, she is constantly at war with her family, and she is in an incredible rush to grow up. Her race to maturity is the trait focused on in Joyce Carol Oates Where Are You Going, Where Have You Been. It splits Connie into two different personalities: One for home, and one for anywhere that was not home (431). Everything about her?her walk, her smile, and her laugh?metamorphoses as soon as she steps out the front door. The child is hidden, the seductive young woman emerges, and the world of the ?big kids? is more than willing to take her in. This world is what†¦show more content†¦Connie notes from time to time that his feet seem to be deformed in some way. One of his feet seems to be bent inward, and his boots are apparently stuffed with something to fill the extra space. Several artistic works have depicted the Devil as a middle-aged, sharp-featured man who walks on the haunches of a goat . Oates?s periodic referral to Arnold Friend?s foot abnormality suggests a parallel between his portrait and that of Satan. Oates also highlights the aura of evil around Arnold Friend?s appearance by stressing how deathly pale his skin is and how his eyes look like ?holes that are not in shadow but instead in light? (435). The sunglasses that conceal Arnold Friend?s eyes also drive Connie to a degree of queasiness, mainly because all she can see in them is a distorted reflection of herself. He could be looking at anything: her deep brown eyes, her quivering body, or perhaps her very soul. The devices that Arnold Friend uses to tempt Connie also suggest that he is the Devil. As the Devil beguiled Eve with a shiny and mysterious apple in Milton?s Paradise Lost, so does Arnold Friend beguile Connie with his shiny and mysterious car. Connie finds the car attractive not only for its dazzling golden paint job but also for the epigrams that Arnold Friend has written on its various parts. Some are humorous, such as the line that appears above a dent in the rear fender: ?Done by crazy woman driver.? Others are more appealingShow MoreRelatedArnold Friend Symbolizes the Devil in Where are you Going, Where Have you been? by Joyce Carol Oates533 Words   |  3 PagesIn the story â€Å"Where are you Going, Where Have you been?† Joyce Carol Oates tells us about a fifteen year old girl named Connie. Connie is confronted by a young man who is trying to persuade her to take a ride with him. He introduces himself as Arnold Friend and kindly asks her to come with him but she refused. He then threatens Connie and her family. She is then forced outside and leaves with Arnold Friend. Arnold Friend clearly symbolizes the devil through his physical traits, his knowledge of ConnieRead MoreArnold Friend Analysis1096 Words   |  5 Pagesideas about what or who the Devil is, even among believers. The number of differing sources and translations have led to plenty of inconsistencies, rumors, and assumptions surrounding the Prince of Darkness. Throughout the short story â€Å"Where Are You going, Where Have You Been?†, Arnold Friend is seen as a symbolic Satan. Joyce Carol Oates uses dialogue, characterization, and plot to show the readers how Arnold embodies features of a symbolic Satan. One of the ways Oates shows Friend as a symbolicRead MoreEssay on Arnold Friend669 Words   |  3 Pagesseductive man, or should I say ArN OLD FrIEND with a dark appearance hiding something deeper, something evil? Arnold, posing as a teen-age boy, is none other than the devil himself, which shows in his words and actions, and in his physical traits. From the very beginning of, Joyce Carol Oates, Where are you going, Where Have you been? a certain number of religious references are interspersed throughout. These references help to maintain a biblical feeling, as well as to set a path for FriendsRead More Joyce Carol Oates Where Are You Going, Where Have You Been?1539 Words   |  7 PagesJoyce Carol Oates Where Are You Going, Where Have You Been?   Ã‚  Ã‚  Ã‚  Ã‚  Joyce Carol Oates was born in 1938 in Lockport, New York. She started writing very young and that the age of fifteen she submitted her first novel, but it was rejected for being too dark;. This style of writing is common on many of her works including Where Are You Going, Where Have You Been?; Oates graduated from Syracuse University and then went on to get her masters degree from the University of Wisconsin. Oates turnedRead MoreEssay About Arnold Friend1388 Words   |  6 Pagesstalker is one thing, but having the devil as a stalker is on another level. â€Å"Where Are You Going, Where Have You Been?† is a short story written by Joyce Carol Oates. Through her writing, she expresses the devil with her use of the character, Arnold Friend. Throughout this story, one can tell Arnold Friend is a symbolic Satan through his description, use of language, and his knowledge. Arnold Friend’s physical description resembles Bob Dylan’s appearance, but the devil is known to take on tempting formsRead MoreWhere are you Going? Where Have you Been? by Joyce Carol Oates1100 Words   |  5 PagesWhere Are You Going, Where have you been? is a short story written by Joyce Carol Oates. The 75 year old American author and professor at Princeton University, introduce the story of 15 year old Connie who is rebelling against her mother’s whishes. A very arrogant and selfish girl that in her world the only thing that matters is how many heads she can turn when walking into a room. Through the story life gives her a test, to confront Arnold Friend, the antagonist of the story; who possesses a nefariousRead MoreEssay on Where Are You Going, Where Have You Been1312 Words   |  6 PagesWhere Are You Going, Where Have You Been by Joyce Carol Oates â€Å"Where Are You Going, Where Have You Been†, is one of the many short stories written by Mrs. Joyce Carol Oates that has become highly recognized. It was inspired by a magazine story about a serial killer. It quickly it became very popular andwas even the basis for the 1985 hit movie, â€Å"SmoothTalk†. Like many other short stories and novels written by Joyce Carol Oates, â€Å"Where Are You Going, Where Have You Been† is a story thatRead More Critical Analysis of Where Are You Going, Where Have You Been?857 Words   |  4 PagesIn Where Are You Going, Where Have You Been? the author, Joyce Carol Oates, essentially asserts that the nuances of ones personality are not generated from within, but rather shaped by external circumstances. This is an argument whose justification is abundantly clear in the inner conflict of Connie, the protagonist of the book. The source of that struggle is her unstable relationship with her family, which ultimately results in her identity conflict. As one who always been deprivedRead MoreAnalysis of â€Å"Where Are You Going, Where Have You Been?† Essay1018 Words   |  5 PagesComp II 30 April 2011 Analysis of â€Å"Where Are You Going, Where Have You Been?† by Joyce Carol Oates In 1966, Joyce Carol Oates published her short story â€Å"Where Are You Going, Where Have You Been?†. Oates was inspired to write this story after reading about a serial killer that was referred to as â€Å"The Pied Piper of Tucson†. Oates was disturbed by the number of teenagers that this killer was able to persuade to help him and keep his secrets (Oates 1). Oates uses irony, imagery, and symbolism toRead MoreThe Devil in Disguise: Comparing and Contrasting the Devil Figure in Where Are You Going; Where Have You Been? The Man in the Black Suit and Young Goodman Brown671 Words   |  3 PagesThe   Devil   in   Disguise    â€Å"Even before he reached me, I recognized the aroma baking up from the skin under the suit--the smell of burned matches. The smell of sulfur. The man in the black suit was the Devil.† (King) A common theme among depictions of The Devil is that of unusual physical attributes. The Devil is depicted in three different stories (Joyce Carol Oates’ ‘Where Are You Going, Where Have You Been?’, Nathaniel Hawthorne’s ‘Young Goodman Brown’, and Steven King’s ‘The Man